The Three Forks School Board recently heard an update on the ongoing renovation/addition project.
Andy Becker, Project Manager for Hulteng CCM, told the board that the total money spent on the project is $5.5 million, roughly 25 percent of the total.
Current upcoming work listed by Becker is wall framing in the elementary school and on the slab on the high school project.
Becker said the weather is always a risk in Montana, and the arrival of structural roof joists is a long wait item and will not arrive at the school until January 17.
He added they had been told the roofing insulation and mem...